Hi All Experts,
My question for above post is if the person in workcenter has operating time of hrs a day, when I give 4hrs & 1day duration against the person in Pesron assignment tab why is date shifting to next day i.e 23.12.2014 in cn50 report (after scheduling).
The work should complete on 22.12.2014 considering 4hrs of work which is less than operating time of 6hrs a day.
Thanks & regards,
Sudhindra